The Surface Seal project, a $160,000 effort approved by the Edwardsville City Council, will kick off the morning of Friday, July 30. The work will include asphalt surface sealing of approximately four miles of streets south of K-32. These streets were previously crack sealed in preparation for this project. The work is expected to last from July 30 to August 4. Please avoid parking on the street during the project in the affected areas, which include:
Woodend Rd.
Blake St.
4th St. (Delaware to River Falls Rd.)
Blake St. cul-de-sac
River Falls Rd.- River Dr.
5th St. (Pacific to Newton)
6th St. (Pacific to Newton)
7th St. (Pacific to Beach)
8th St. (Delaware to Beach)
Newton St. (4th to 9th)
Beach St. (4th to 9th)